Direct Hourly Costs C182 C210 C310
Fuel @ $2.00/gal $26 $32 $60
Oil @ $4.00/qt 1 1 2
Scheduled 50-hour maintenance 4 6 10
Unscheduled maintenance 4 6 10




Amortized Hourly Costs C182 C210 C310
Engine overhaul $10 $14 $28
Miscellaneous engine maintenance 3 4 7
Vacuum pumps 1 1 3




Total Hourly Costs $49 $64 $120




Annual Fixed Costs C182 C210 C310
Annual inspection $2,000 $3,000 $6,000
Insurance 1,500 2,000 3,000
Propeller overhaul @ 5 years 300 500 1,600
Paint and interior @ 5 years 1,600 2,000 2,400
Avionics maintenance, gyro OH 800 1,000 1,200
Hangar 1,800 1,800 3,000
Recurrent training 1,000 2,000 5,000




Total Annual Fixed Costs $9,000 $12,300 $22,200





C182 C210 C310
Total Cost/Hr @ 100 hours/year $139 $187 $342
Total Cost/Hr @ 200 hours/year 94 126 231
Total Cost/Hr @ 300 hours/year 79